Project Status
Key Dates
Project Management Office
Project Health Indicators
Project Timeline
Initial planning phase in progress
System design and architecture planning
Development and configuration
Testing and validation
System deployment and go-live
Recent Updates
Current Project Metrics (September 3, 2026)
Overall Project Completion: 90%
Reports: 490 of 498 completed (98%)
Integrations: 37 of 42 completed (88%)
Go Live Blockers
· EPAFS - (on R and I log) ORU will need to use EIP. Forms to replace some page builders, if some EPAFs will be used. There is approximately 12 that need to be built. (Sherry). Per ORU's update - to be completed by 8/10
In-flight Engagements:
Technical Account Manager
EUP (Ethos User Provisioning)
PROD Ready
Envisions
Completed - ORU testing printed checks and transcripts (ask David to conform about transcripts)
Experience Custom Cards -7/21 email sent about Training card
ISE - David working with TD Client and ORU
· Degree Works
o Term Structure adjustments - awaiting quote/SOW.
· Insights
o No weekly meetings scheduled - working adhoc
· Integration Development - 37 of 42 integrations completed (88%); 5 remain in progress
o Mabee Center - 15% complete; Owner: Stebin Jose; Planned Finish: September 29, 2026
o Touchnet - 85% complete; Owner: Paul Hanson; Planned Finish: September 11, 2026
o Transact Campus - 20% complete; Owner: Paul Hanson; Planned Finish: September 10, 2026
o Clear Company - 20% complete; Owner: Ellucian; Planned Finish: September 18, 2026
o Fitbit - 85% complete; Owner: Jacob Swanson; Planned Finish: September 4, 2026
· Mock Migrations:
o Mock 5 (Final):
o Data migration is scheduled for: August 10 - August 21, 2026
o ORU will need to provide/upload Banner and Application Database files by the Thursday, 8/6
o Saas Production Environment will be offline: During this time, work can continue in SaaS Test, Insight Reports, Integrations
o David Smith to complete validation steps, and then Saas Production should be available 8/28, for Ellucian and ORU to begin review of the system.
• Day in the Life:
o Dates confirmed with cloud team. 4 hours duration
· Wednesday, September 23rd (1:00pm CT)
• Go-Live Monday 10/12, 2026
SaaS PROD offline: Thursday 10/8, starting in AM to prepare environment for go live
Go live/ Cutover information on the Smartsheets - updates in progress
Code freeze notes - as provided in email
•EIP- resources secured to begin 8/31, when the system becomes avaiable after the final mock. Resources to assis with consulting and QandA only; ORU is building their own workflows and forms.
BCM meeting to be scheduled. BCM demo recording released 7/29 to ORU team to review and to come with questions for the next meeting with Caleb, David and ORU IT resource.
ISE/TD Client - David continued to work with Paul/ORU on TD Client issues
Go live pre and post documentation provided to ORU
• ISE/TD Client - David working through issues with TD client; Testing/review with ORU
• Go live blockers listed in the Executive Summary column